Rehabilitation of Runway 11-29.
This project is sponsored by the Port Authority of NY & NJ.
It comprises a $16 million project, consisting of 60,000 Hot Mix Asphalt (HMA), 10,000 CY Portland Cement Concrete, extensive electrical and and lighting system upgrades.
Construction began mid 2008. Final completion took place mid 2009.