This project is worth $11.6 million and consisted of milling, pavement repairs, resurfacing, shoulder back up and other work along 16.5 miles of the NYS Thruway (I-87) in Orange Co, NY.
Work began in October 2007 and was completed mid 2008.
The paving element of the project involved placing 73, 450 tons of Hot Mix Asphalt and the shoulder back up involved 31, 635 tons of stone.